See below for the week 25 construction update!
• New auxiliary gym scoreboards installed.
• New auxiliary gym basketball hoops and backboards installed.
• New auxiliary gym batting cage installed.
• New auxiliaries gym floor is being prepped and the new maple floor will start being installed soon.
•TechEd addition floors are prepped and ready for the epoxy finishing.
• Painting is almost done on exterior doors and bollards.
• Walls are going up on the new 4K-5K wing addition.
• Footings are completed.
• Rooms have been prepped in the back metal building and are ready for demolition.
• Teacher collaboration has begun to decide what classroom furniture suits our districts needs best. Great work was done by all!