The following is the progress being made during Week 17 of the facilities update project:
• Temporary doors are being installed on the TechEd addition until the new overhead doors are installed.
• Groundbreaking has begun on the new 4K-5K addition!
• Windows & service doors have been installed in the new TechEd addition.
• New railing on the mezzanine and new stairway have been installed in the Ag Shop.