The following progress was made during Week 19 of the facilities update project:
• New curbs have been poured on Ogden Ave. as well as behind the new auxiliary gym
• Foundation on the new Elementary School is being dug out and footings are starting to be placed
• Auxiliary gym corridor has walls up now
• Auxiliary gym bathrooms walls are now framed as well as new door frames are installed
• Auxiliary gym roofing is 75% complete
• Auxiliary gym roof drains are being installed and the mezzanine roof is complete
• The Ag Shop is almost completely painted
• New auto shop has new auto exhaust fans installed