We’re committed to keeping you updated on the facilities update project! Here’s what was worked on during the week 6 construction process:
• Phase 1 roofing replacement is moving along perfectly ahead of schedule
• Room 311 is now being renovated into a science room
• Caulking and sealing walls are nearly completed
• Walls are starting to form on the TechEd/Ag addition
• Electrical upgrades are going into the Metals Shop area
• The Main HS gym floor is now completely removed and the foundation is being prepped for the new Maple floor to begin install in the next week or so
• Summer cleaning is moving along as scheduled