The facilities update project continues to progress nicely. We are still on or ahead of schedule! This week's update includes the following:
• Fire proofing has begun along the far east corridor as well as the TechEd shops
• Ag shop fire proofing near completion in the existing lab area
• Floor drains being installed in the Ag lab area as well
• New mechanicals are being installed for the TechEd wing this week
• Structural steel being installed in the new TechEd addition
• Roof decking is also being installed in the new TechEd addition
• Room 311 and 308-310 are starting to get finishing touches as painting has begun
• Auxiliary gym walls are still being erected at a great pace