We’re making progress on the facilities update project! Here’s what happened this week:
• High School main gym floor is almost completely removed
• High School baseball & softball dugouts are now painted
• Wall removed from between 308-310 New 2D Art
• Wall removed from between 317-318 New Ag Classroom
• Phase 1 roofing project well underway
• Walls starting to form on both Tech Ed addition & Auxiliary Gym
• High School exterior Cougar Blue painting is 95% completed
• HS Gymnasium is completely sound system. It's really awesome!
• Summer cleaning is underway
• Soil boring/testing is underway at the Middle School
#BeCougarProud